Generator Installation & Control Panel

Generator Installation & Control Panel

Replacement Petbow AP800 Generator Control System The Brief To supply, deliver, install and commission a fourth generator identical to the existing sets. To design, manufacture, deliver, install and commission a replacement five set generator-to-generator control panel incorporating the generator change-over controls. The Project The standby power generation system comprised of 3 off Petbow AHBX400 400kW

Replacement Petbow AP800 Generator Control System

The Brief

To supply, deliver, install and commission a fourth generator identical to the existing sets.

To design, manufacture, deliver, install and commission a replacement five set generator-to-generator control panel incorporating the generator change-over controls.

The Project

The standby power generation system comprised of 3 off Petbow AHBX400 400kW generators. Each generator is powered by a Cummins KTA19 G4 industrial diesel engine, which is flexibly coupled to a Leroy Somer LSA47.1 L10 C6/4 alternator.

Each generator is controlled locally by a set mounted control panel and remotely by the Petbow AP800 generator-to-generator paralleling control system. Each generator parallels on to a dead bus and feeds out to the switchgear panel. The project comprised of two sections. The first section was the installation and
commissioning of a fourth generator. The generator had to be identical to the original 3 sets because of the synchronising characteristics.

Each of the 3 original generator set mounted control panels then had to be severely modified to operate with the new control system.

The second section was to design, manufacture, deliver, install and commission a replacement generator synchronising panel. The new generator remote synchronising panel was designed to mount in to the same position as the original panel. This was a requirement because of the lack of manoeuvrability within the LV switch room and the load cables already being in a set position.

The panel was designed to incorporate a firth generator for future expansion, a mimic diagram that was to include the mains incomer status for both H.V. Transformers and the change-over controls for all of the existing switchgear.

The common control section had to be designed to offer load level demand to shut down or re-instate generators on high or low load conditions. All of the functions within the generator control system for synchronising, breaker opening / closing and automatic starting had to be fully automated with the option of being able to carry out all of the functions manually.

Related posts

Generator packages for top performing NHS Foundation Trust

Generator packages for top performing NHS Foundation Trust

The customer: Established in 1931 and currently based in Central London. They specialise in the complete installation of Mechanical &...

[vc_row][vc_column width="1/1"]
[/vc_column][/vc_row]