Life safety Generator Control Panel and MCCB Panel upgrade for state of the art serviced offices

Life safety Generator Control Panel and MCCB Panel upgrade for state of the art serviced offices

Life safety Generator Control Panel and MCCB Panel upgrade for state of the art serviced offices at exclusive address in London Customer: A reputable provider of Building Services Maintenance specialising in the operation of Mechanical and Engineering maintenance of landmark buildings in London for the private sector. Project: Due to an existing long term relationship

Replacement Generator Paralleling Control Panels

Replacement Generator Paralleling Control Panels

Replacement of FG Wilson Woodward GCP 30 Generator Controller Due to a long and successful working relationship with the client we were asked to quote for the supply and installation of replacement generator paralleling control panels for six generators currently fitted with FG Wilson paralleling control panels incorporating Woodward GCP30 controllers which are now obsolete.

Generator Package Upgrade for London Magistrates Court

Generator Package Upgrade for London Magistrates Court

Generator Package Upgrade for London Magistrates Court The customer required The Generator Company to provide a generator package upgrade for a well-known magistrate’s court in North London. The project required us to design, manufacture, package, deliver and commission a 1 off 350kVA prime rated open generator with Volvo TAD 532 GE diesel engine, along with

650kVA Standby Generator Set

650kVA Standby Generator Set

Back-up generator for new first class retail and office development in London The Customer   UK’s leading independent building services company. The Site Eastern end of Oxford Street, known as the ‘poor relation’ to the West End of London. This new 90,700 sq. ft. first class retail and office development, with 47,100 sq. ft. of

1650kVA Standby Generator Installation for new mixed use property in London

1650kVA Standby Generator Installation for new mixed use property in London

1650kVA Back-up generator for new high-quality mixed-use property located in a prestigious and historical area of London The Customer   UK’s leading independent building services company. The Site A 1970’s built office building was demolished in late 2014 to make way for high-quality commercial, residential and retail development in the heart of Mayfair, London. The

Standby Generator Upgrade for Global Technology Co.

Standby Generator Upgrade for Global Technology Co.

1000kVA Standby Generator Upgrade, Installation & Commissioning Our client, one of the largest communication technology companies in the world, contacted us to provide a suitable solution for a 1000kVA standby generator upgrade to incorporate some of the site’s existing services and associated equipment at one of their UK datacentres. For this client, using their award-winning

Generator Power System Upgrade at Grade II London Offices

Generator Power System Upgrade at Grade II London Offices

3 x 500kVA Generators Replaced During Modernisation of Mayfair Offices With extensive refurbishments taking place at grade II listed offices in Mayfair, London, The Generator Company were approached for the provision of an upgrade to the property’s existing back-up generator power system. This formidable Grade II listed property, was originally constructed between 1665 to 1673